Accurately identifying risk in the early phases of construction projects is pivotal to managing budgets, timelines, and client expectations. Through recent internal analysis and case reviews, Active Estimating has uncovered key risk indicators that emerge before subcontractor engagement, particularly during the budgeting and pre-bid stages. These findings emphasize the importance of early-stage visibility into labor metrics, scope clarity, and production feasibility.
In-depth reviews of preconstruction documents have revealed how inconsistencies between budgetary assumptions and actual bid line item details can snowball into systemic project risk. One analysis demonstrated that a project initially scoped at 98,885 labor hours under budgeting parameters was ultimately bid at 123,035 labor hours — a 25% increase. This disconnect often stems from siloed estimating processes and a lack of dynamic labor unit benchmarking.
Based on compiled project reviews and estimating trends, several recurring factors signal elevated early-phase risk:
Rather than relying solely on final bid reviews, Active Estimating leverages data-driven intelligence to analyze labor unit performance during the conceptual and schematic phases. This approach enables early identification of:
For example, in the reviewed 425,000 sq. ft. scope, the budget allocated 27,500 labor hours to Exterior Framing. Upon bid finalization, that number escalated to 36,800 hours — a clear sign of underestimated risk factors such as weather exposure, sequencing inefficiencies, and material availability impacts.
Cross-departmental collaboration and real-time data review have proven vital in mitigating labor overruns. By comparing forecasted and actual labor hours at multiple design stages, estimating teams can apply rolling adjustments and improve bid accuracy. This iterative process enhances forecast integrity while reducing exposure to late-phase redesign costs or operational overruns.
Proactive identification of labor variance and scope complexity indicators can significantly improve financial performance and stakeholder trust. By implementing refined labor metrics and phase-specific intelligence, firms can shift from reactive estimating to a predictive, controlled budgeting process.
For additional resources or to request a full whitepaper on this risk assessment methodology, contact the team below.
Active Estimating
508 2nd Street, Suite 208
Davis
California
95616
Rich Schoener
richard@activeestimating.com
(877) 982-2848
https://www.activeestimating.com/drywall-estimating-software
Schedule a personalized demo to see how Active Estimating can work for your specific needs.